10 Oct 2024
The initial construction works are progressing smoothly with the perimeter piling around the boundary having been completed. This significant milestone has enabled us to begin bulk excavation, with approximately 700m3 of earthworks being removed from site each day. This process will help us reach the foundation depths necessary across the site and form the lowest […]
READ MORE07 Aug 2024
Over the last few months piling works continue to progress on site with approximately 80% of retention piles installed, which is forecasted to be complete by the end of this month. This progress has enabled the commencement of bulk excavation which is currently underway in the north-eastern corner of the site. Additionally, the new temporary […]
READ MORE
16 Jan 2024
Following strong off-the-plan sales, construction has commenced at our iconic Scarborough address. The milestone was celebrated with a ‘turning of the sod’ event on site this week with key stakeholders. Urbis Town Planning Director Tim Dawkins, DevelopmentWA Executive General Manager Planning and Transition Matt Ryan, Edge Visionary Living Directors Gavin Hawkins and David Hillam, City […]
READ MORE15 Dec 2023
Edge is thrilled to announce the official appointment of Roberts Co to undertake construction of The Dunes. The award-winning Tier 1 builder has undergone a period of significant growth over the past five years, drawing upon decades of experience in construction contracting and Founding Director Andrew Roberts’ rich family heritage and industry reputation throughout Australia. […]
READ MORE